Commissioning
Commissioning means that you check that the unit works correctly before you rely on its data. Do this indoors first.
Check the readings
On the data platform, check that every sensor on the unit sends values. With the factory setting, the unit reports every 5 minutes. Wait for at least one full cycle before you judge the readings. Wait several hours if electrochemical gas modules are new.
Use a power adapter for indoor tests. Indoor light cannot keep a solar-powered unit running long enough for a test.
Commissioning checklist
| Check |
|---|
| The unit starts and the LED completes the start sequence. |
| The unit is registered and visible on the data platform. |
| Every internal module and external sensor sends a reasonable value. |
| The reporting interval is set as the project requires. |
| The signal strength (RSRP) at the installation site is Fair or better. |
| The serial number, pairing ID, installation ID and firmware version are written down. |
| For MCERTS use: model SB8202 with PM module SB4102, 5-minute interval, and on-site calibration planned. See Measurement data. |
| The enclosure is closed correctly. No cable is caught in the seal. |
| The mounting parts are tight, the unit is the right way up, and unused connectors have their caps. |
| There is at least 20 cm (8 in) between the unit and people at the final location. |
| The site operator has received the manual and the compliance information. |
Switching off
Switch the unit off before you move it, ship it or open the enclosure.
- Disconnect external power. The unit does not switch off while external power is connected.
- Press and hold the power button for 4 seconds.
- The status LED shows steady red for about 30 seconds and then goes off. The unit is now off.
- ·Six red blinks: there was an error during shutdown and the unit restarts. Try again.
- ·Red for about 30 seconds, then three green blinks: external power is still connected and the unit stays on.
Once off, take the unit to its site and follow Deployment.